Montreal Olympics: Case Study of Project Management Failure

Based on the journal, and on your understanding of the project, answer the questions below: DOI: 10.1061/(ASCE)CF.1943-5509.0000332 Journal title: “1976 Montreal Olympics: Case Study of Project Management Failure” 1. Was building the stadium at this location and at this time the best approach to have been chosen? Provide rationale using PV, NPV, IRR, B/C. 2. Use the initial and final WBS to create two high-level budgets for the project. These two should be the initial and final budgets. Explain the difference. 3. Was there adequate quality management processes in place (including quality planning, quality assurance and quality control)? Provide rationale.4. Was there adequate outsourcing in the project? Provide rationale.